TEİ B700 PART MANUFACTURING BUILDING

EMPLOYER :TEİ TUSAŞ MOTOR SAN. A.Ş.
CONSTRUCTION AREA : 16.000 m2





TEİ B700 PART MANUFACTURING BUILDING

EMPLOYER :TEİ TUSAŞ MOTOR SAN. A.Ş.

STARTING DATE OF THE PROJECT : 12.03.2008

COMPLETION DATE OF THE PROJECT : 14.11.2008

LOCATION : ESKİŞEHİR

PROJECT VALUE : 5.790.425,52 $

DETAILS :

Factory Building with 12.666 m2 total construction area has been completed within a short term as 8 months and delivered 4 months earlier than the term indicated in the contract.
1175 tons of Steel
11.603 m2 roof covering
2443 m2 siding
11.650 m2 epoxy application
1353 tons of iron production
15.051 m3 concrete production
22.500 m2 mold production